GFO Issue 414, Article Number: 5
Award Rates of C19RM 1.0 vs C19RM 2.0 (as of December 2021)
1A .C19RM maintained a rapid pace in approving grant requests.
1B. The mechanism had been strengthened when compared with C19RM 1.0.The robustness of the review and approval process was enhanced in: internal finance review, Investment Committee approvals, Board reporting, C19RM integration into existing grants, procurement, disbursements, guidance and tools, and alignment of investment categories.
1C. The process of allocating funds across portfolios has been strengthened. However, there are some limitations in the design of the process and in the data used to inform the qualitative adjustment process.
1D. There was a strong perception of inclusion in the C19RM 2.0 request and approval process. The positive impact of inclusion efforts was noted in the OIG survey of CCM stakeholders:
1E.The External Review process was established and well-executed but fast implementation exposed challenges.
To put this into context, the report explains that External Reviews were conducted by GAC and CTAG partners (including WHO, GAVI, Stop TB and UNICEF) in parallel with the internal reviews performed by Global Fund Secretariat teams. The External Reviews assessed: (a) the technical robustness of applications; (b) the alignment/coordination of investments across donors and national stakeholders; and (c) alignment with WHO technical guidance and national preparedness plans. The overall approach was to: (i) notify External Reviewers that a new Funding Request was ready for review and request them to provide their input within three working days; (ii) share Funding Request documents via an online platform; (iii) collect External Reviewers’ inputs using online tools and consolidate them into a summary that was shared with Country Teams; and (iv) synthesize the External Reviewers’ inputs and Country Team responses and provide the synthesis to the Investment Committee (IC) to inform the award decision.
The implementation challenges noted in the audit report were:
1F. For oxygen investments, prioritizing speed and the lack of in-house technical capacity impacted the anticipation of downstream risks.Despite the initial gaps in technical knowledge and understanding, the Secretariat made significant efforts and investments in improving its internal technical understanding of oxygen provision, to enhance support to countries.
1G. There was – and remains – a need to continue to strengthen people, tools, and systems to support C19RM 2021 across its life cycle.
2A. As of December 2021, the M&O framework had not been fully implemented (see the figure below); significant components of upstream monitoring and reporting had been in place for several months, however, country analysis and reporting based on results from Pulse Checks and Spot Checks remained in-progress:
2B. The Board had set out detailed requirements with respect to upstream monitoring and oversight and the Secretariat materially met all these requirements through monthly Board reporting and through developing and utilizing multiple channels to support engagement and knowledge sharing with the Board on C19RM 2.0.
Most Board survey respondents highlighted that they were satisfied with the frequency (88%) and amount (83%) of information provided by the Secretariat on C19RM 2.0. Most respondents (59%) said engagement and transparency had improved compared to C19RM 1.0. However, perspectives relating to the disclosure of operational challenges at the Secretariat and country level were less favourable with the following respondent percentages rating Secretariat disclosure as poor/very poor:
One reason for the less favourable perspectives on disclosure of operational challenges is that while there were clear Board requirements for reporting on progress for the approval phase, there were no prescriptive details around key reporting expectations for the implementation stage. It is also important to highlight that as the M&O framework is not fully operational, there are still gaps in the data received from countries, including on operational challenges.
2C. The M&E framework’s design is comprehensive but is not yet fully operational. With data collection at a nascent stage, the OIG could not comprehensively assess the implementation and effectiveness of the M&E framework.
2D. Mandatory minimum LFA assurance on in-country supply chain was not implemented, leading to limited assurance over system capacity and gaps.
2E. There are limitations in the oversight of post-IC approval changes for grants.
2F. There are issues with reporting on procurement activities, leading to gaps in the visibility of progress. Given procurement’s key role within C19RM 2021, a greater emphasis was put on monitoring and tracking both PPM and non-PPM procurements which resulted in new reporting processes and requirements.
2G. There is no centralized reporting process to track the status of legal requirements and management actions on contingent disbursements.
3A. C19RM 1.0 utilization was not as expected at country level due to procurement bottlenecks. As of 30 June 2021, use of C19RM 1.0 funding across all portfolios was 47% based on the latest information available, with significant variations between individual countries.
COVID-19 exposes pre-existing challenges with procurement supply management (PSM) at country level. In six of the OIG sample countries, significant PSM challenges were highlighted as limiting the impact of C19RM 1.0 funding, with three common PSM root causes: (i) global production and supply side factors; (ii) in-country local procurement capacity and processes; and (iii) regulatory and administrative challenges at country level.
3B. There was limited Secretariat visibility to effectively monitor C19RM 1.0 funds: (a) The lack of visibility on absorption levels hindered mitigation of absorption risk. (b) The inability to isolate C19RM 1.0 funding from grant flexibilities and to obtain detail on procurements impacted monitoring.
3C. Despite early warning signs from C19RM 1.0 regarding utilization and procurement bottlenecks, significant time was taken to convert an initial request into orders, increasing the risk of under-utilization in the later stages of C19RM 2.0.
4A. C19RM 2.0 is exposed to more volatile global changes in epidemiology and is reliant on fast-changing, sometimes contradictory information when approval decisions are made. As a result, as new information is collated and analysed, there is a need to ensure this is quickly and continuously factored into decision making during implementation. The mechanism needs to be more agile than for core grants to respond to changes throughout its life cycle, which is significant as C19RM 2.0 will support implementation until December 2023.
4B. The lack of a cross-portfolio process is likely to lower C19RM’s agility in years two and three of its life cycle (i.e., during the implementation phase). It impacts the Global Fund’s ability to reprioritize savings in line with regional and global changes in epidemiology and to respond to country-specific challenges around absorption and shifts in the funding landscape. To tackle this, portfolio optimization processes for savings across portfolios need to be defined. To support this, there is a need to determine the principles of what constitutes savings or new funding, through a new portfolio optimization process.
4C. Portfolio optimization processes are needed to adapt to low absorption and COVID-19 disruptions.
4D. There is a need to enhance key systems and tools that support rapid savings identification and portfolio optimization.
4E. C19RM 2.0 introduced a two-tier approach to accessing funding: the full funding process and the fast-track application process. The purpose of fast-track was to ensure that countries’ urgent needs for COVID-19 commodities were supported, although it was acknowledged that even with immediate order placement, there would be significant lead times before essential commodities arrived in country. Essentially the mechanism was not designed for acute emergency response.
4F. The low uptake of fast-track funding and lack of differentiation in timelines impacted its overall usefulness. As of December 2021, in response to 36 applications, $591 million had been awarded through the fast-track approach representing 66% of the available funding that could have been accessed through this method:
Across the 10 OIG sampled countries, the speed of fast track to support countries from initial request to purchase order was 76 days, versus 84 days for full funding. These data highlight an underused fast-track mechanism, as well as some limitations in administering applications quickly.
Country capacity to engage across two types of requests quickly and effectively was noted as a limiting factor to accessing the mechanism in a timely manner. 75% of CCM respondents to the OIG survey highlighted capacity challenges to manage the C19RM 2.0 processes alongside their existing workload.
4G. There are structural imitations that impact the Global Fund’s ability to support COVID-19 acute emergency response.
COVID-19 has had an overwhelming impact on all stakeholders, highlighting a widespread lack of emergency preparedness to deal with a pandemic of this nature and scale. Differing peer approaches highlight potential further avenues for the Global Fund to explore, with the aim of enhancing C19RM’s speed and agility. But equally, there are numerous trade-offs and risks associated with each approach that would have to be carefully considered. Given the impact of COVID-19 on the global supply chain for key commodities and products, it is unclear if any alternate approach would ensure a faster response, and various peer organizations have faced different challenges due to their models.
Your email address will not be published. Required fields are marked *
Comment *
Name
Email
Article Id
Issue Details
Article Number: 1
2022-06-29
Article Number: 2
Article Number: 3
Article Number: 4
Article Number: 6
Article Number: 7
Article Number: 8
Article Number: 9
Categories*
Catégories*
Subscribe to our newsletter below and never miss the latest updates.
Subscribe to our weekly newsletter below.
Friend's Email Address
Your Name
Your Email Address
Comments
Send Email